Dilip Buildcon (DBL) has received a Provisional Completion Certificate (PCC) for four lanes of Dhrol-Bhadra Patiya section of NH-151A in Gujarat on November 4, 2023 under a public-private partnership (PPP).
The authority issued a CCP and declared the project suitable for commercial operation as of September 25, 2023.
The work included four lanes of the Dhrol-Bhadra Patiya section of NH-151A (between Ex. km 5+700 to km 13+600 of SH-25) and the Bhadra Patiya-Pipaliya section of NH- (between Ex. km 73 +000 to km 44+800 and for example km 38+350 to 24+000 of CSH-6) in the state.
The project, worth Rs 882.00 crore, was executed on design, build, operate and transfer (DBOT) basis. On October 28, 2021, DBL was commissioned to work on the project with a delivery time of 730 days. The project should be completed by October 27, 2023.