An initiative by the government to support the domestic industry by way of a bulk order from state-owned NTPC, is also fraught with delays. The tender said only those companies having domestic manufacturing facilities could participate. The order for 11 sets of
660 megawatts (Mw) was initiated in October 2009, but there has been very slow progress due to litigation. While turbine and generator sets have been awarded, the contract for boilers is yet to be. “Though the long-term demand outlook is good, in the last six months not many projects have been financially closed due to a number of uncertainties and this is likely to continue," said Sabyasachi Majumdar, vice-president at rating agency Icra.
405
799
1699
3399
3061
6122
1799
1999
949
1999
299
599
3450
3899
5656
9049
1099
1485
4227
6340
17629
35297
21169
42297
4011
6417